Local Law 11 explained: FISP requirements, covered buildings and the 2026 changes

Local Law 11 is the reason so much of New York is under scaffolding. This guide covers what the Facade Inspection Safety Program requires, which buildings it covers, who signs the report, what changed in 2025 and 2026, and what it means for the teams performing the repairs.

Last checked: Oct 29, 2026

Key facts

  • Who buildings taller than six stories; a DOB-approved QEWI examines the facade and files in DOB NOW: Safety
  • Cycle 10 February 21, 2025 to February 20, 2030; the window follows the last digit of the tax block
  • Next cycles Local Law 49 of 2025 (in effect October 1, 2026) lets DOB set intervals of 6 to 12 years by rule
  • Filing penalties $1,000 a month when late; $5,000 a year when not filed
  • Results Safe, SWARMP or Unsafe, each with its own timeline

What is Local Law 11 in New York City?

Local Law 11 is the common name for the Facade Inspection Safety Program (FISP). It requires owners of buildings taller than six stories to have the exterior walls and their appurtenances examined by a DOB-approved Qualified Exterior Wall Inspector (QEWI) and to file the report in DOB NOW: Safety. The report classifies the facade as Safe, SWARMP or Unsafe, and each classification starts a different timeline. The current cycle, Cycle 10, runs from February 21, 2025 to February 20, 2030.

Key considerations

A filing requirement that becomes a construction project

The law requires an inspection; what it produces is a scope. The QEWI identifies conditions, and someone must price, permit and build the repairs. That second half is where the project manager’s work lies, and it is defined by the report, not by the law.

Taller than six stories

Coverage depends on height alone — not use or age. Within Cycle 10, the filing window depends on the last digit of the tax block number.

The inspection interval is changing

Local Law 49 of 2025, effective October 1, 2026, replaced the fixed five-year cycle in AC §28-302.2 with periodic intervals of 6 to 12 years to be set by DOB rule, and moved the first examination of new buildings to the eighth year. Until DOB adopts the implementing rule, the Cycle 10 filing windows remain in effect.

The QEWI signs; the owner and contractor carry it

The QEWI seals the report, but everything the report triggers — the sidewalk shed, scaffold permits, protection plans and the repairs themselves — falls to the owner and the contractor.

Deadlines once a shed goes up

When a sidewalk shed goes up for an unsafe facade and its initial permit was issued on or after January 12, 2026, Local Law 51 of 2025 adds three repair milestones, each with a one-time penalty. The dates and the amounts are in our sidewalk shed permit guide; how to request an extension, in our LL51 milestone extension guide.

Three programs, three calendars

Since Local Law 126 of 2021, the same building may also require an annual parapet observation and, if it contains a parking structure, periodic condition assessments — every six years through 2027 and every four years from 2028 under Local Law 71 of 2024.

The cost of non-compliance

$1,000 per month for late filing and $5,000 per year for failure to file (1 RCNY §103-04). Once a report is filed, an Unsafe condition that is not corrected, and a SWARMP condition still unrepaired at the next cycle, carry penalties of their own: see Safe, SWARMP or Unsafe.

Checklist: from report to repairs

  1. Find the sub-cycle from the last digit of the tax block (Cycle 10).
  2. Read the QEWI report: each Unsafe and SWARMP item is scope with a date.
  3. Plan Unsafe repairs inside 90 days, or have the QEWI file the extension (Safe, SWARMP or Unsafe).
  4. If a shed goes up, put the Local Law 51 milestones on the schedule (shed permit).
  5. Add the annual parapet observation and any parking-structure assessment to the building’s calendar.

Sources

Checked against the official text on October 29, 2026.