How to request an LL51 sidewalk shed milestone extension (from November 2, 2026)
From November 2, 2026, requests to extend the 5-month, 8-month and 24-month repair milestones that Local Law 51 of 2025 sets for sidewalk sheds on FISP buildings are filed in DOB NOW: Safety. When the window opens and closes, who files, what the owner signs, the three fees and where DOB posts the decision.
Last checked: Oct 29, 2026
Key facts
- From November 2, 2026: DOB NOW: Safety › Sidewalk Shed Milestone Extension (LL51)
- Milestones 5, 8 and 24 months from the initial shed permit (AC §28-220.2.1; 1 RCNY §102-07)
- Window opens 60 calendar days before the 5-month deadline; closes 20 calendar days before the deadline being extended
- Who an RDP submits; the owner logs in to attest to the Statements and Signatures
- Fees $410 (5 months), $465 (8 months), $1,425 (24 months) · 1 RCNY §101-03
How do you request an LL51 milestone extension in DOB NOW?
From November 2, 2026, a Registered Design Professional (RDP) files it in DOB NOW: Safety with the Sidewalk Shed Milestone Extension (LL51) button, choosing the 5-month, 8-month or 24-month milestone and finding the shed permit by address, BIN or permit number. A request can go in no earlier than 60 calendar days before the 5-month deadline and no later than 20 calendar days before the deadline it extends. The owner’s information comes from the shed permit, and the owner logs in to attest to the Statements and Signatures; then Pay to File and Proceed to Pay submit the fee: $410, $465 or $1,425. Approved and denied requests are listed in the DOB NOW Public Portal under Safety: Compliance Filings.
Key considerations
Which sheds have milestones
The milestones apply to sidewalk sheds issued and installed for facade work required by Article 302 of the Administrative Code — FISP, or Local Law 11 — and they are counted from the issuance of the initial shed permit. Local Law 51 of 2025 covers sheds whose initial permit was issued on or after January 12, 2026; the milestones and the penalty for missing each one are in our sidewalk shed permit guide.
The three milestones
DOB’s notice says what each milestone asks for, counted from the initial shed permit: at 5 months, the associated FISP/Local Law 11 filing submitted in DOB NOW — the complete construction documents for the repair; at 8 months, the GC permit for that filing submitted — a complete permit application; at 24 months, a Letter of Completion (LOC) issued for the repair work. Each milestone takes its own extension request, whether the requests are filed separately or at the same time (1 RCNY §102-07(h)).
When a request can be filed
A request for any of the three milestones can be submitted no earlier than 60 calendar days before the first deadline — the 5-month one — and no later than 20 calendar days before the deadline it extends. All three windows open on the same day; each closes 20 days before its own deadline. A shed whose initial permit was issued on January 10, 2027 has its 5-month deadline on June 10, 2027: its 5-month extension can be filed from April 11 to May 21, 2027. The table below has the three windows.
Who files, and what the owner does
A Registered Design Professional — a Professional Engineer or a Registered Architect — must submit the request. The owner’s information fills in from the shed permit, and the owner has to log in to DOB NOW: Safety and attest to the Statements and Signatures before the request is paid. Line up the owner’s login early: the window closes 20 days before the deadline.
Step by step in DOB NOW: Safety
Log in to DOB NOW: Safety, click Sidewalk Shed Milestone Extension (LL51) on the dashboard and select the milestone: 5-month, 8-month or 24-month. Search for the shed permit by address, BIN or permit number and complete all the required fields. Once the owner has attested to the Statements and Signatures, select Pay to File at the top of the request to preview each page of the application, then Proceed to Pay to submit the payment.
What the RDP attaches
Under 1 RCNY §102-07(h), a request carries, where they apply: a brief reason the milestone cannot be met, the anticipated schedule through completed repair work with the month and year of completion, a contract showing the scope of repairs, a summary of the permits the repair needs, and any other document that explains why the timeline cannot be met. A 5-month request also carries progress repair drawings or, where the drawings are not developed yet, a narrative of the scope of work; for a 24-month request, the contract also shows a timeline to complete the repairs.
How much time an extension gives
For the 5- and 8-month milestones, DOB may grant extensions of up to 180 days at a time; for the 24-month milestone, a single extension of a longer period (1 RCNY §102-07(h)(1)). If DOB issues objections, a revised request is due within 14 days; when it is not revised in time, or is still not accepted after two notices, the request is denied and a new one can be filed with a new fee. The one-time penalty for a missed milestone applies unless an extension request is filed under the rule; if a request is denied and no new one is filed and accepted, the owner may face it (§102-07(g), (h)(5)–(6)).
The fees
The filing fee depends on the milestone (1 RCNY §101-03): $410 for the 5-month request, which buys time to submit complete construction documents for the facade repair; $465 for the 8-month request, time to submit a complete permit application for the repair; and $1,425 for the 24-month request, time to complete the repair within the two-year period. It is paid inside the request, with Pay to File and then Proceed to Pay.
Where the decision shows up
Every approved or denied Sidewalk Shed Milestone Extension request is visible in the DOB NOW Public Portal under Safety: Compliance Filings — the place to confirm a decision, including on a shed someone else filed for. For help with DOB NOW, the notice points to DOB’s training page at nyc.gov/dobnowtraining (training sessions, step-by-step guides, user manuals and videos) and to nyc.gov/dobhelp.
Not a FISP1 or FISP2
A milestone extension is its own request. The FISP1 and FISP2 extensions that cover the 90-day repair clock of an Unsafe condition are filed by the QEWI (after a FISP Unsafe report); the milestone extension is filed by the RDP under Sidewalk Shed Milestone Extension (LL51), with its own fee.
The three windows for a shed issued January 10, 2027
Counted from the initial shed permit: every request window opens 60 calendar days before the 5-month deadline and closes 20 calendar days before its own deadline.
| Milestone | Deadline | First day to file | Last day to file |
|---|---|---|---|
| 5 months: the FISP/Local Law 11 filing submitted | June 10, 2027 | April 11, 2027 | May 21, 2027 |
| 8 months: its GC permit submitted | September 10, 2027 | April 11, 2027 | August 21, 2027 |
| 24 months: the Letter of Completion issued | January 10, 2029 | April 11, 2027 | December 21, 2028 |
Checklist: before a milestone is missed
- From the initial shed permit’s issue date, put the 5-, 8- and 24-month deadlines on the schedule.
- Mark the day the request window opens — 60 calendar days before the 5-month deadline — and each milestone’s last day to file, 20 calendar days before it.
- If a milestone is at risk, give the RDP the reason, the schedule through completion, the repair contract and the list of permits the repair needs.
- Have the RDP file in DOB NOW: Safety: Sidewalk Shed Milestone Extension (LL51), the milestone, then the shed permit by address, BIN or permit number.
- Get the owner to log in and attest to the Statements and Signatures.
- Pay to File, preview each page, then Proceed to Pay: $410, $465 or $1,425.
- Answer any objections within 14 days, and check the decision in the Public Portal under Safety: Compliance Filings.
Sources
- NYC DOB Service Notice, “Local Law 51 of 2025 – Follow up #2: Sidewalk Shed Milestones Extension Requests in DOB NOW” (October 27, 2026)
- 1 RCNY §102-07: sidewalk shed permit renewal requirements and penalties (effective August 13, 2026)
- 1 RCNY §101-03: DOB fees (shed progress report $90; facade extension and waiver fees)
- Local Law 51 of 2025: facade repair milestones once a shed goes up (AC §28-220.2.1)
- NYC DOB, DOB NOW Training (training sessions, step-by-step guides, user manuals and videos)
Checked against the official text on October 29, 2026.
Related guides
- Sidewalk shed permits in NYC: when one is required, and the 90-day ruleA shed is required for facade work more than 40 ft above curb level and whenever a dangerous condition exists. Since February 2026, permits last 90 days, renewals require an RDP progress report, and stalled sheds carry penalties that DOB expects to start imposing in early 2027.
- NYC sidewalk shed renewal (2026 rules): the RDP report, the $220 fee and the weekly logSince August 13, 2026, a shed renewal needs an RDP’s in-person examination and progress report: $130 plus $90, or $220, and a $2,500 penalty when no acceptable report is filed. The contractor keeps the weekly work log.
- After a FISP Unsafe report: the 90-day clock, FISP1 and FISP2 extensions, and taking the shed downUnsafe means 90 days to repair, then a FISP1 and FISP2 extension every 90 days — never for money reasons, and gaps are penalized. The amended report within two weeks of finishing, and the two ways a shed comes down early.