Sidewalk shed permits in NYC: when one is required, and the 90-day rule

A sidewalk shed is required for facade work more than 40 ft above curb level, and whenever a dangerous condition exists. Since February 2, 2026, shed permits last 90 days, and every renewal must document the progress of the work the shed protects.

Last checked: Oct 29, 2026

Key facts

  • When facade work more than 40 ft above curb level, and any dangerous condition at any height
  • Permit term 90 days, renewed by hand in DOB NOW (permits issued or renewed since February 2, 2026)
  • Each renewal $220 with an RDP’s progress report, for most sheds — see shed renewal
  • Stalled work $10, $100 or $200 per linear foot per month from the second renewal; DOB expects to start imposing it in early 2027
  • Code BC 3307.6; AC §28-105.8.1; AC §28-220 · filed in DOB NOW: Build

When does NYC require a sidewalk shed?

Facade work more than 40 ft above curb level requires a sidewalk shed, or an approved alternative protective measure, under BC 3307.6.2. The shed must cover the sidewalks within a distance from the work equal to half the height of the facade work. A shed is also required whenever a dangerous condition exists, regardless of height. The shed is filed in DOB NOW: Build, and under Local Law 48 of 2025, permits issued or renewed on or after February 2, 2026 are valid for 90 days and must be renewed manually.

Key considerations

The 40 ft threshold

Facade work more than 40 ft above curb level requires a shed. Below 40 ft, a shed is generally not required unless a dangerous condition exists.

How much sidewalk it covers

The shed covers the sidewalks within a distance equal to half the height of the facade work, and the decking extends 5 ft beyond that zone — or 20 ft at both ends when the unenclosed work is more than 100 ft above the ground (BC 3307.6.3).

The 40 ft cap for plain facades

For maintenance or repair of a facade with no setbacks or projections above the second story, the decking need not cover sidewalks more than 40 ft from the building, unless the Commissioner orders otherwise (BC 3307.6.3, exception 3, added by Local Law 47 of 2025; clarified in DOB Buildings Bulletin 2026-015).

Emergency protection

A shed erected to protect the public from an unsafe condition may go up before the permit is issued, provided the permit application is submitted within two business days after the work begins (AC §28-105.4.1, item 1). DOB’s older Sidewalk Sheds web page still says 24 hours; the Code says two business days.

An unknown height is not a “no”

When the drawings do not state the building height, the prudent assumption is that a shed is required until the height is confirmed.

90-day permits since February 2026

Local Law 48 of 2025 took effect on January 12, 2026, and DOB NOW began issuing 90-day permits on February 2, 2026. Permits issued or renewed since then expire every 90 days and do not renew automatically. Each renewal now needs a Registered Design Professional’s in-person examination and progress report and costs $220 (BC 106.8.3; 1 RCNY §102-07, in effect since August 13, 2026). What the report covers, the $2,500 penalty when it is missing and the contractor’s weekly work log are in Sidewalk shed renewal (2026 rules).

Penalties when work stalls

Beginning with the second renewal, if work is not in progress the owner may be assessed $10 per linear foot of shed per month for sheds standing less than three years, $100 for three to less than four years, and $200 for four years or more; only that last tier is capped, at $6,000 a month (AC §28-220.1). The permit cannot be renewed until the penalties are paid. DOB expects to begin imposing these penalties in early 2027.

Repair deadlines for unsafe facades

On a building subject to FISP (more than six stories) whose initial shed permit was issued on or after January 12, 2026, Local Law 51 of 2025 sets three milestones for repairing the unsafe facade, each with a one-time penalty: $5,000 if complete construction documents are not filed within 5 months of the initial shed permit, $10,000 if a complete permit application is not filed within 8 months, and $20,000 if the repairs are not completed within 2 years (AC §28-220.2.1; 1 RCNY §102-07(g)). DOB’s notice of October 27, 2026 states them for DOB NOW: the FISP/Local Law 11 filing submitted, its GC permit submitted and a Letter of Completion issued for the repair. When a milestone cannot be met, the RDP requests an extension, in DOB NOW: Safety from November 2, 2026; the window, the fees and the steps are in our LL51 milestone extension guide.

Exemptions

The 2025 penalty provisions do not apply to sheds installed for permitted new building, enlargement or demolition work, and the renewal penalties do not apply to one- and two-family homes. Neither of those needs the renewal progress report (1 RCNY §102-07(c)).

New design requirements

For sheds whose construction documents were submitted on or after August 15, 2025, Local Law 47 of 2025 raised the minimum clear ceiling height from 8 ft to 12 ft (between 8 and 12 ft where 12 ft would interfere with required light, air or egress, as noted by the RDP) and expanded the permitted colors beyond hunter green to metallic gray, white or a color matching the facade. DOB has also proposed a rule for six new sidewalk shed designs (City Record, August 17, 2026); it has not been adopted.

An owner-provided shed still needs checking

When the owner supplies the shed, confirm that its permit is current, in whose name it is held and when it expires. No shed may stand without a permit (BC 3307.6.1), so agree with the owner who renews it every 90 days.

Checklist: before the shed goes up

  1. Confirm the height of the facade work: more than 40 ft above curb level means a shed.
  2. For an unsafe condition, put the protection up first and submit the permit application within two business days.
  3. Get the shed lighting’s electrical permit first: DOB wants it before the shed permit (shed lighting).
  4. Put the permit’s expiration on the schedule and plan a renewal every 90 days (shed renewal).
  5. For an unsafe facade on a building over six stories, put the 5-month, 8-month and 2-year repair milestones on the schedule, with their extension windows (milestone extension).
  6. When the owner supplies the shed, get its permit number, holder and expiration date in writing.