The DOB permit covers the shed or the scaffold, not the street around it. Material, a container, a crane or a pedestrian walk on the street, or a closed stretch of sidewalk or roadway, each takes its own DOT permit from NYCStreets. Which ones a facade job needs, what they cost, and the holiday embargo that starts November 15.

Last checked: Oct 23, 2026

Key facts

  • DOB or DOT the DOB permit covers the shed or scaffold; the roadway, a sidewalk closure, containers and cranes need DOT
  • Permits Building Operations and Construction Activity (02 series), one per activity, through NYCStreets
  • Cost and term $50 and 90 days for most; a crane permit runs one week, plus a $100 inspection fee
  • Sidewalk an Occupancy of Sidewalk permit when fences take more than 3 ft from the property line or the clear path drops below 5 ft
  • Holiday embargo November 15, 2026 to January 2, 2027, 6 am to 11:59 pm, in the listed areas

When does a facade job need a DOT permit?

Whenever the job uses the street — roadway or sidewalk — beyond what the DOB permit covers. For sheds and scaffolds, DOT lists placing or storing material or equipment on the street (including a shed or scaffold whose footings and barrier extend past the curb into the roadway), temporarily closing the sidewalk or roadway, building a temporary pedestrian walk in the roadway, and crossing the sidewalk with a vehicle where there is no approved drop curb or driveway. Containers, cranes and trailers on the street need permits too. These Building Operations and Construction Activity permits are issued online through NYCStreets to registered permittees, typically after the DOB permit; most cost $50 and run 90 days, and each activity needs its own permit.

Key considerations

DOB covers the structure, DOT the street

DOT’s rule of thumb in its Street Works Manual: all work within the street requires a DOT permit. When putting up, taking down or maintaining a shed or scaffold, you may need DOT construction activity permits in addition to the DOB shed permit. DOT reviews the application for a Building Operations and Construction Activity permit, and a valid DOB permit is typically required before applying.

The permits a facade job uses

These are the 02 series. The ones a facade job reaches for: 0201 Place Material on Street, 0202 Crossing Sidewalk, 0203 Place Crane or Shovel on Street, 0204 Place Equipment Other Than Crane or Shovel, 0205 Place Shanty or Trailer on Street, 0208 Temporary Pedestrian Walk, 0211 Occupancy of Roadway, 0214 Place Container on the Street and 0215 Occupancy of Sidewalk. The manual lists each at $50 for 90 days, except the crane permit: one week, plus a $100 inspection fee; the fees are set in the Highway Rules’ schedule of fees (34 RCNY §2-03). A separate permit is required for each construction activity unless the Highway Rules or the permit’s stipulations say otherwise.

When the sidewalk narrows

An Occupancy of Sidewalk permit is required when a fence obstructs more than 3 feet from the property line, or when a clear path of at least 5 feet cannot be kept for pedestrians. An Occupancy of Roadway permit covers closing all or part of one or more lanes. A full roadway closure starts with DOT’s request form, emailed at least 10 days before the closure. All pedestrian paths around a work zone must be accessible and comply with the Americans with Disabilities Act.

Cranes

A DOT crane permit is required for every crane or derrick operating in the street on building work under DOB’s jurisdiction, with a narrow exception for certain truck cranes covered by a construction activity permit. A crane may also need DOB permits, and moving it through the city may take over-dimensional vehicle permits from DOT.

NYCStreets

Registered permittees apply for, pay for and print DOT permits online at nycstreets.net. To register, contact DOT’s Permit Management Office at constructionpermits@dot.nyc.gov. DOT’s Office of Construction Mitigation and Coordination (OCMC) reviews these permits and writes their stipulations — the conditions printed on the permit — and the work must follow them, including the hours and days work may take place.

Hours and noise

A permit’s stipulations can limit the hours and days of work in the street. Work outside 7 am to 6 pm on weekdays needs after-hours approval, and DEP requires the site’s Construction Noise Mitigation Plan to be in place before an after-hours permit is sought from DOB or DOT. For the DOB side, see After-Hours Variance; for the plan, noise and dust plans.

Embargoes, and the holiday one

DOT imposes construction embargoes for major events and the winter holidays: active permits in the area are suspended and no new ones are approved, unless DOT grants a waiver. The 2026 Holiday Construction Embargo runs from 6 am to 11:59 pm daily, from Sunday, November 15, 2026 through Saturday, January 2, 2027, in the listed areas — in Manhattan, for example, from 30th to 66th Street, river to river. Routine work in the street there is suspended unless OCMC approves it; emergency work needs an emergency number.

Inspections and violations

DOT’s Highway Inspection and Quality Assurance (HIQA) inspectors check how construction material and equipment are placed and used at building sites, and whether the work follows the permit’s stipulations, and they issue violations when it does not. DOT’s violations are heard at OATH, under the DOT penalty schedule in Chapter 3 of Title 34 of the Rules of the City of New York.

Checklist: before the shed or scaffold goes up

  1. Mark everything that will sit past the property line: shed or scaffold footings and barriers, containers, material, a trailer, a crane.
  2. Measure the sidewalk: more than 3 ft taken from the property line, or under 5 ft of clear path, means an Occupancy of Sidewalk permit.
  3. Register with NYCStreets if the company is not a permittee yet.
  4. Once the DOB permit is issued, apply in NYCStreets for each activity’s permit.
  5. Read each permit’s stipulations — hours, days, walkways — and brief the crew.
  6. Check DOT’s embargo list before scheduling street work, especially from November 15.