Supported scaffold permits in NYC: the 40 ft threshold
A supported (pipe or frame) scaffold 40 ft or more in height requires a DOB permit. Below 40 ft, a permit is generally not required — provided the scaffold meets every condition of the code exemption.
Last checked: Oct 23, 2026
Key facts
- Permit at 40 ft or more, filed in DOB NOW: Build (BC 3314.2)
- Below 40 ft exempt only when all six conditions of BC 3314.2, Exception 4, are met
- Any height an outrigger scaffold, hoisting equipment over 2,000 lb or a design load over 75 psf removes the exemption
- Training 32-hour course plus an 8-hour refresher every 4 years for installers, removers and their supervisors; a 4-hour course for every user
When does a supported scaffold need a permit in NYC?
A permit is required for a supported scaffold 40 ft or more in height, filed in DOB NOW: Build. The exemption in BC 3314.2 (Exception 4) applies only when all six of its conditions are met: the scaffold is less than 40 ft tall, is not an outrigger scaffold, carries no hoisting equipment rated over 2,000 lb, is not designed for loads over 75 psf, uses side-arm or end-arm brackets only to support workers, and, where it is more than four times as tall as its base is wide, is restrained per BC 3314.9.1. When the drawings do not state the height, treat the permit as required until the height is confirmed.
Key considerations
40 ft or more
The exemption covers only scaffolds less than 40 ft in height, so a supported scaffold of 40 ft or more requires a permit.
Height is not the only condition
An outrigger scaffold, hoisting equipment over 2,000 lb, or a design load above 75 psf removes the exemption at any height. So do side-arm or end-arm brackets used for anything other than supporting workers, and a scaffold more than four times as tall as its base that is not restrained per BC 3314.9.1.
How height is measured
A scaffold staged on top of a sidewalk shed or other temporary structure is measured including that structure. On a roof or setback, height is measured from the roof or setback to the top of the scaffold.
Supported or suspended
On taller buildings a full-height pipe scaffold is often impractical, and a suspended scaffold dropped from the roof is the likely method — a different filing under the Suspended Scaffold work type in DOB NOW.
Training
Workers who install, adjust, repair, maintain or remove a supported scaffold 40 ft or more in height — and those supervising them — must complete a DOB-approved course of at least 32 hours, with an 8-hour refresher every four years (BC 3314.4.5.1). Every worker who uses a supported scaffold needs a 4-hour course.
The drawings rarely specify it
Scaffold permits are filed by the contractor after award, so bid documents rarely name the access method. Inferring it from the building height is reasonable; assuming it is not.
Checklist: supported scaffold
- Measure the height including any shed or structure the scaffold stands on; on a roof or setback, from that level.
- Under 40 ft, check all six exemption conditions; if one fails, file the permit.
- Confirm the access method with the scaffold contractor before the bid is final.
- Check the crew’s training: the 32-hour course and its refresher for installers, removers and supervisors, the 4-hour course for every user.
Sources
- 2022 NYC Building Code, Chapter 33: Safeguards during construction or demolition
- NYC DOB, 32-Hour Supported Scaffold Installer and Remover course requirements
- NYC DOB, 4-Hour Supported Scaffold User and Refresher course requirements
Checked against the official text on October 23, 2026.
Related guides
- Suspended scaffold filings: from CD5 to DOB NOW, and the 24–48 hour noticeSince November 15, 2023, suspended scaffolds are filed in DOB NOW under the Suspended Scaffold (SC) work type, replacing the CD5. DOB must be notified 24 to 48 hours before installation and removal.
- Sidewalk shed permits in NYC: when one is required, and the 90-day ruleA shed is required for facade work more than 40 ft above curb level and whenever a dangerous condition exists. Since February 2026, permits last 90 days, renewals require an RDP progress report, and stalled sheds carry penalties that DOB expects to start imposing in early 2027.