Work above an adjoining roof in NYC: BC 3309.10 protection and access
When work takes place above a neighboring roof, NYC requires that roof, its skylights and rooftop equipment to be protected for the duration of the project — and installing that protection usually requires the neighbor’s written permission to enter.
Last checked: Oct 23, 2026
Key facts
- Notice in writing at least 60 days before the work; a second notice 30 to 45 days before if there is no answer (BC 3309.1.1)
- Access a license from the adjoining owner (BC 3309.2); if refused, a court petition under RPAPL §881
- Protection from 48 in above the roof: 2 in flame-retardant foam under 2 in plank, covered by plywood (BC 3309.10)
- Extent the height of the highest working level, up to 20 ft unless DOB requires more
- Cost paid by the party doing the work
Do I need the neighbor’s permission to work above their roof in NYC?
Protection of the adjoining roof is required under BC 3309.10, and installing it requires access to the neighboring property. That access requires a license from the adjoining owner (BC 3309.2); if the owner refuses, the building owner may petition the court for a license under RPAPL 881. Because it depends on a third party with no deadline, this is one of the items that most often delays facade work at lot lines.
Key considerations
Who provides the protection
The party performing the work protects the adjoining roof, its skylights, outlets and rooftop equipment for the duration of the project, at its own expense. If the adjoining owner refuses access, responsibility for protecting the roof shifts to that owner.
Secured against wind
Roof protection must be secured to prevent dislodgement by wind.
From 48 inches above the roof
Where work occurs 48 in or more above the adjoining roof, the protection consists of 2 in of flame-retardant foam under 2 in of flame-retardant wood plank laid tight, covered by flame-retardant plywood, unless the Commissioner accepts an equivalent. It extends horizontally by the height of the highest working level, up to 20 ft unless DOB requires more.
Physical and legal
The roof is protected physically, and the access is documented legally. Both are required before work begins.
Start early: 60 days’ notice
When access is required, written notice must be provided to the adjoining owner at least 60 days before work begins, describing the work, the schedule, inspections and monitoring, and the protection to be installed; if there is no response, a second notice is required 30 to 45 days before the start (BC 3309.1.1). Negotiations commonly involve license fees, engineering review, insurance, indemnification and bonding.
Where it arises
Rear and side elevations on tight lots are where this requirement most often affects the schedule.
Checklist: work above a neighbor’s roof
- Mark every elevation where the work rises above an adjoining roof, skylight or rooftop equipment.
- Send the written notice at least 60 days before the start: the work, the schedule, inspections and monitoring, and the protection.
- No answer: send the second notice 30 to 45 days before the start.
- Negotiate the license: fees, engineering review, insurance, indemnification and bonding.
- Install the protection, secured against wind, before work starts above the roof.
Sources
- 2022 NYC Building Code, Chapter 33: Safeguards during construction or demolition
- NYC DOB, Lot-line construction presentation (2023 Build Safe | Live Safe Conference)
Checked against the official text on October 23, 2026.
Related guides
- Supported scaffold permits in NYC: the 40 ft thresholdA supported (pipe or frame) scaffold requires a permit at 40 ft or taller. Below 40 ft it generally does not — if it also meets all six conditions of the BC 3314.2 exemption.
- Suspended scaffold filings: from CD5 to DOB NOW, and the 24–48 hour noticeSince November 15, 2023, suspended scaffolds are filed in DOB NOW under the Suspended Scaffold (SC) work type, replacing the CD5. DOB must be notified 24 to 48 hours before installation and removal.
- Ordinary repair or work permit: the distinction that drives the scheduleBrick repointing, sealant, crack injection and cleaning require no work permit. Parapet rebuilds, lintels, shelf angles, cornices, steel and pinning do, and so does stone or terra-cotta patching on buildings over six stories. Where the line is drawn.