Ordinary repair or work permit: the distinction that drives the schedule
Repointing, sealant replacement and cleaning qualify as ordinary repair and generally require no work permit. Parapet rebuilds, lintel replacement, shelf angles, cornices and structural steel do. This guide explains where the line falls.
Last checked: Oct 23, 2026
Key facts
- No permit repointing, sealant and caulking, crack injection and cleaning (1 RCNY §101-14, Table 3)
- Stucco no permit up to 1 in thick and 40 ft high
- Brick no permit for single-wythe replacement up to 10 sq ft in any 100 sq ft, 150 sq ft in all
- Stone, terra cotta patching needs a permit only on buildings over six stories; pinning needs one at any height
- Code AC §28-105.1, §28-105.4.2 · filed in DOB NOW: Build
Does facade repointing need a DOB permit in NYC?
Brick repointing, sealant and caulking, crack injection and cleaning are listed in 1 RCNY §101-14, Table 3, as facade work that does not require a permit. Work beyond those limits requires a Registered Design Professional and a work permit: parapet rebuilds, masonry reconstruction, lintel or shelf-angle replacement, cornice replacement, new guardrails, structural steel, concrete repair, new expansion joints and masonry pinning. Patching spalls or cracks in stone or terra cotta needs a permit only on buildings subject to FISP (more than six stories).
Key considerations
What does not require a permit
Brick repointing (or other unit masonry); masonry crack repair by injection of repair mortar; cleaning, coloring or painting of masonry and concrete; sealant, caulking and regrouting; trowel-applied stucco up to 1 in thick and up to 40 ft high; and same-height replacement of an existing guardrail or parapet — for masonry parapets, limited to 10 sq ft in any 100 sq ft. Individual bricks can also be replaced without a permit in the single outside wythe: up to 10 sq ft, no more than 4 ft horizontally in any 100 sq ft of wall, and 150 sq ft in total on all facades.
Beyond ordinary repair
Parapet rebuilds beyond the Table 3 limits, masonry reconstruction, lintel replacement, shelf-angle work, masonry pinning, cornice replacement, new guardrails or railings, structural steel, concrete and slab repair, roof deck replacement, shoring, underpinning, new expansion joints, and stucco thicker than 1 in or above 40 ft.
Stone and terra cotta: it depends on the work
Table 3 requires a permit to patch spalls or cracks in exterior stone or terra cotta only on buildings subject to FISP, which are those taller than six stories (AC §28-302); for lower buildings the table does not list it. At any height, a permit is required to pin displaced stone or terra cotta to the structure, or to replace stone or terra-cotta ornament with a different material. Cleaning, coloring or painting stone or terra cotta needs no permit.
An existing DOB filing settles it
If the drawings already carry a DOB job number, the permit question has been answered — confirm which work types the filing covers.
Other filings still apply
Even ordinary repair can require a sidewalk shed, a scaffold permit or, on a landmark building, LPC approval.
The schedule impact
A work permit adds plan review and objection responses to the front of the schedule. Identifying it at bid protects the start date.
Checklist: permit or not
- Check every scope item against 1 RCNY §101-14, Table 3.
- Count the stories: on a building over six stories, stone or terra-cotta patching needs the permit.
- Flag the items that need one at any height: pinning, lintels, shelf angles, parapet rebuilds, cornices, steel, concrete and new expansion joints.
- Check whether the drawings already carry a DOB job number, and which work types it covers.
- Add the shed, scaffold and LPC filings the job needs even when the repair itself is ordinary.
Sources
- 1 RCNY §101-14: work that does and does not need a permit (Table 3: facades)
- NYC Administrative Code, Title 28, Chapter 1: Administration (permits, §28-105; TPP, §28-120)
- NYC Administrative Code, Title 28, Chapter 3: Maintenance (FISP §28-302, parapets §28-301.1.1, parking structures Article 323)
Checked against the official text on October 23, 2026.
Related guides
- Filing a facade repair job in DOB NOW: Build: who files what, and in what orderThe RDP files an Alteration with the General Construction work type, DOB reviews it, the contractor pulls the work permit, and the job is signed off. Where sheds and scaffolds fit, and what must be ready first: LPC drawings, asbestos forms, the TPP.
- LPC approval for facade work on landmark buildingsLandmark facade work needs one of three LPC permits, filed in Portico. Repointing that needs no DOB permit still needs one. Most Local Law 11 repair that does need DOB is a staff approval, not a hearing.
- Sidewalk shed permits in NYC: when one is required, and the 90-day ruleA shed is required for facade work more than 40 ft above curb level and whenever a dangerous condition exists. Since February 2026, permits last 90 days, renewals require an RDP progress report, and stalled sheds carry penalties that DOB expects to start imposing in early 2027.