LPC approval for facade work on landmark buildings
Landmark facade work needs one of three LPC permits, filed in Portico. Repointing that needs no DOB permit still needs one. Most Local Law 11 repair that does need DOB is a staff approval, not a hearing.
Last checked: Oct 23, 2026
Key facts
- Permits PMW (no DOB permit), CNE (DOB permit, no adverse effect), C of A (public hearing)
- Timing from a complete application: PMW 20, CNE 30, C of A 90 working days
- Order filed in Portico; where a DOB permit is needed, LPC comes first
- Mortar at an individual landmark, a mortar analysis when a substantial part of the primary facade is repointed
- Code AC §§25-305 to 25-310; 63 RCNY chapter 2
Which LPC permit does a facade repair need?
If the building is an individual landmark or sits in a historic district, the facade work needs an LPC permit. There are three. Staff decides which one after reviewing the application. You do not pick it.
Permit for Minor Work (PMW). Exterior work that does not need a DOB permit and that staff finds restorative or appropriate: masonry cleaning, repointing, patching, restoring a detail that already exists. Staff review. No community board and no hearing.
Certificate of No Effect (CNE). Work that does need a DOB permit and that staff finds has no adverse effect on protected features. No hearing. LPC’s permit guidebook names facade restoration under Local Law 11 as a CNE. A lintel, a parapet rebuild, or a pinned facade that already has a DOB filing is usually this.
Certificate of Appropriateness (C of A). The scope changes a protected feature and does not fit the rules for a staff permit: a cornice rebuilt to a new profile, a feature taken off the wall, a substitute material staff will not accept. Community board, then a public hearing. This is the one that moves a start date by a season.
Key considerations
“Before DOB” is only half the sequence
Where a DOB permit is required, LPC comes first. Where it is not, the filing is a PMW. Table 3 of 1 RCNY §101-14 can take the DOB permit off a repointing job and still leave LPC on it.
The clock is not one number
A complete CNE that meets the rules can often be approved within 10 business days. The legal outside date is 30 business days once LPC confirms the application is complete. From a complete application: PMW 20 working days, CNE 30, C of A 90. An incomplete set starts none of them.
Repointing: the method is part of the permit
Mortar matches the historic mortar and is less strong and more permeable than the brick or stone. Type N on later buildings; a softer, lime-rich mix is common on 19th-century masonry. Joints are cut by hand with a chisel. Power tools only on wide horizontal joints, supervised so the joint is not widened. On an individual landmark, a mortar analysis is required when a substantial amount of the primary facade is repointed (63 RCNY §2-11).
The mockup is a hold
If the permit requires samples, work does not start until staff approves them. Cleaning method, raked joint, patch, replacement unit — at least two options. Clean the historic surface next to the panel first. At or above 45°F for 72 hours after installation. Photos in sun and in shade. Street View does not count. Price the panel, the cure, and a return visit ahead of the drop.
Cleaning has a ceiling
500 psi on masonry, 300 psi on cast iron. Sandblasting is prohibited.
Terra cotta is repaired before it is replaced
Minor spalls are patched and glazed to match. An anchor is galvanized or stainless and concealed. A GFRC replica is a substitute: if staff will not take it inside a CNE, it is a C of A.
Check the map before the number goes out
Individual landmarks and historic districts go through the same LPC permit process, but the criteria are stricter at an individual landmark: replacements cannot use substitute materials (63 RCNY §2-11), and a substantial repoint needs a mortar analysis. Whether a building is in a historic district is answered by LPC’s Discover NYC Landmarks map: check the lot itself, not the block or the building next door.
Checklist: LPC
- Check the lot on LPC’s Discover NYC Landmarks map: individual landmark, historic district or neither.
- File in Portico with a complete set: an incomplete one starts no clock.
- Where the work needs a DOB permit, get the LPC permit first.
- Plan the mockups: at least two options, kept at 45°F or more for 72 hours, photographed in sun and in shade.
- On an individual landmark, budget the mortar analysis and in-kind replacement units.
Sources
- NYC LPC, Permit types
- NYC LPC, Permit for Minor Work
- NYC LPC, Certificate of No Effect
- NYC LPC, Certificate of Appropriateness
- Rules of the Landmarks Preservation Commission, 63 RCNY chapter 2 (§2-11: masonry; PMW §25-310, CNE §25-306, C of A §25-307)
- NYC LPC, Permit Guidebook: Introduction
- NYC LPC, Permit Guidebook, Chapter 1: Restoration
- NYC LPC, Landmark designation (one process for individual landmarks and historic districts)
- NYC LPC, Maps: Discover NYC Landmarks
- 1 RCNY §101-14: work that does and does not need a permit (Table 3: facades)
Checked against the official text on October 23, 2026.
Related guides
- Ordinary repair or work permit: the distinction that drives the scheduleBrick repointing, sealant, crack injection and cleaning require no work permit. Parapet rebuilds, lintels, shelf angles, cornices, steel and pinning do, and so does stone or terra-cotta patching on buildings over six stories. Where the line is drawn.
- Local Law 11 explained: FISP requirements, covered buildings and the 2026 changesWhat the Facade Inspection Safety Program requires, which buildings it covers and who signs the report — including Local Law 49 of 2025, which replaces the five-year cycle with intervals of 6 to 12 years.
- Safe, SWARMP or Unsafe: what each facade report classification requiresUnsafe starts a 90-day clock. SWARMP sets a firm completion date between one and five years out. What each classification commits the owner to — including the 2025 deadlines for sheds.