Safe, SWARMP or Unsafe: what each facade report classification requires

The three FISP classifications and the timeline each one starts. Unsafe requires repairs within 90 days and an amended report within two weeks of completion; SWARMP sets a completion date between one and five years out.

Last checked: Oct 29, 2026

Key facts

  • Unsafe repaired within 90 days of the report; amended report within two weeks of the repairs
  • SWARMP a completion date one to five years out; the same condition is never SWARMP twice in a row
  • Unsafe not corrected $1,000 a month, plus $10 to $40 per linear foot of shed per month in years two to five
  • SWARMP not repaired $2,000 when the next cycle’s report files it as Unsafe
  • Extensions FISP1, then FISP2, filed by the QEWI: $305 each

What is the difference between SWARMP and Unsafe on a NYC facade report?

Unsafe means the condition is a present hazard: it must be corrected within 90 days of filing the report, and an amended report must be filed within two weeks of completing the repairs. SWARMP — Safe With a Repair and Maintenance Program — means the facade is safe today but has conditions that must be repaired by a stated completion date, no less than one year and no more than five years out. Safe requires no action before the next cycle. The three classifications are defined in 1 RCNY §103-04.

Key considerations

Unsafe starts a 90-day clock

Correct the condition within 90 days of filing the report, then file an amended report within two weeks of completing the repairs. Public protection — typically a sidewalk shed — goes up immediately and stays until DOB approves an amended Safe or SWARMP report or a Partial Shed Removal (PSR); finishing the repairs does not by itself let the shed come down. When the repairs need more than 90 days, the QEWI files an extension request in DOB NOW: Safety (FISP1, then FISP2; $305 each). Extensions do not go past the unsafe completion date in the report; moving that date takes a subsequent report.

Report it the same day

An Unsafe condition is reported to DOB at once: call 311, and the QEWI files a FISP3 (Notification of Unsafe Conditions) in DOB NOW: Safety. A missing FISP3 can bring an OATH violation to the QEWI.

An unsafe facade with a shed now has milestones

When the shed’s initial permit was issued on or after January 12, 2026, Local Law 51 of 2025 adds three repair milestones counted from that permit, each with a one-time penalty. The dates and the amounts are in our sidewalk shed permit guide; how to request an extension, in our LL51 milestone extension guide.

SWARMP is a commitment with a date

The report tells the City the building is safe today and names the date by which the conditions will be repaired — not less than one year and not more than five. The same condition at the same location cannot be classified SWARMP in two consecutive cycles: if it is still not repaired at the next inspection, that report must classify it Unsafe, and the owner then owes a $2,000 penalty (1 RCNY §103-04).

What an uncorrected Unsafe costs

Unless an extension covers the period, an owner who has not corrected an Unsafe condition 90 days after the report owes $1,000 a month. From the second year DOB adds $10 per linear foot of shed per month, rising to $20, $30 and $40 in years three, four and five. The penalty runs until DOB accepts the amended report, the shed is removed and the permits are signed off (1 RCNY §103-04).

The classification owners underestimate

SWARMP reads like “no problem,” and it is not. It is a scheduled obligation with a filing attached, and it is often why a shed that went up “temporarily” is still standing years later.

The QEWI decides

The classification is the inspector’s professional judgment under 1 RCNY §103-04. What the project manager controls is the evidence and the repair scope that follows from it.

Checklist: after an Unsafe report

  1. The same day: call 311, and have the QEWI file the FISP3 in DOB NOW: Safety.
  2. Put up the public protection the QEWI recommends.
  3. Plan the repairs to finish within 90 days, or have the QEWI file the FISP1 so the time after day 90 is covered.
  4. Keep the shed until DOB approves the amended Safe or SWARMP report or a Partial Shed Removal.
  5. File the amended report within two weeks of finishing the repairs.