Safe, SWARMP or Unsafe: what each facade report classification requires
The three FISP classifications and the timeline each one starts. Unsafe requires repairs within 90 days and an amended report within two weeks of completion; SWARMP sets a completion date between one and five years out.
Last checked: Oct 29, 2026
Key facts
- Unsafe repaired within 90 days of the report; amended report within two weeks of the repairs
- SWARMP a completion date one to five years out; the same condition is never SWARMP twice in a row
- Unsafe not corrected $1,000 a month, plus $10 to $40 per linear foot of shed per month in years two to five
- SWARMP not repaired $2,000 when the next cycle’s report files it as Unsafe
- Extensions FISP1, then FISP2, filed by the QEWI: $305 each
What is the difference between SWARMP and Unsafe on a NYC facade report?
Unsafe means the condition is a present hazard: it must be corrected within 90 days of filing the report, and an amended report must be filed within two weeks of completing the repairs. SWARMP — Safe With a Repair and Maintenance Program — means the facade is safe today but has conditions that must be repaired by a stated completion date, no less than one year and no more than five years out. Safe requires no action before the next cycle. The three classifications are defined in 1 RCNY §103-04.
Key considerations
Unsafe starts a 90-day clock
Correct the condition within 90 days of filing the report, then file an amended report within two weeks of completing the repairs. Public protection — typically a sidewalk shed — goes up immediately and stays until DOB approves an amended Safe or SWARMP report or a Partial Shed Removal (PSR); finishing the repairs does not by itself let the shed come down. When the repairs need more than 90 days, the QEWI files an extension request in DOB NOW: Safety (FISP1, then FISP2; $305 each). Extensions do not go past the unsafe completion date in the report; moving that date takes a subsequent report.
Report it the same day
An Unsafe condition is reported to DOB at once: call 311, and the QEWI files a FISP3 (Notification of Unsafe Conditions) in DOB NOW: Safety. A missing FISP3 can bring an OATH violation to the QEWI.
An unsafe facade with a shed now has milestones
When the shed’s initial permit was issued on or after January 12, 2026, Local Law 51 of 2025 adds three repair milestones counted from that permit, each with a one-time penalty. The dates and the amounts are in our sidewalk shed permit guide; how to request an extension, in our LL51 milestone extension guide.
SWARMP is a commitment with a date
The report tells the City the building is safe today and names the date by which the conditions will be repaired — not less than one year and not more than five. The same condition at the same location cannot be classified SWARMP in two consecutive cycles: if it is still not repaired at the next inspection, that report must classify it Unsafe, and the owner then owes a $2,000 penalty (1 RCNY §103-04).
What an uncorrected Unsafe costs
Unless an extension covers the period, an owner who has not corrected an Unsafe condition 90 days after the report owes $1,000 a month. From the second year DOB adds $10 per linear foot of shed per month, rising to $20, $30 and $40 in years three, four and five. The penalty runs until DOB accepts the amended report, the shed is removed and the permits are signed off (1 RCNY §103-04).
The classification owners underestimate
SWARMP reads like “no problem,” and it is not. It is a scheduled obligation with a filing attached, and it is often why a shed that went up “temporarily” is still standing years later.
The QEWI decides
The classification is the inspector’s professional judgment under 1 RCNY §103-04. What the project manager controls is the evidence and the repair scope that follows from it.
Checklist: after an Unsafe report
- The same day: call 311, and have the QEWI file the FISP3 in DOB NOW: Safety.
- Put up the public protection the QEWI recommends.
- Plan the repairs to finish within 90 days, or have the QEWI file the FISP1 so the time after day 90 is covered.
- Keep the shed until DOB approves the amended Safe or SWARMP report or a Partial Shed Removal.
- File the amended report within two weeks of finishing the repairs.
Sources
- 1 RCNY §103-04: periodic inspection of exterior walls (FISP)
- NYC Administrative Code, Title 28, Chapter 3: Maintenance (FISP §28-302, parapets §28-301.1.1, parking structures Article 323)
- NYC DOB, Façade compliance (Unsafe conditions, FISP1/FISP2/FISP3, public protection)
- NYC DOB, Façade fees and penalties
- Local Law 51 of 2025: facade repair milestones once a shed goes up (AC §28-220.2.1)
Checked against the official text on October 29, 2026.
Related guides
- After a FISP Unsafe report: the 90-day clock, FISP1 and FISP2 extensions, and taking the shed downUnsafe means 90 days to repair, then a FISP1 and FISP2 extension every 90 days — never for money reasons, and gaps are penalized. The amended report within two weeks of finishing, and the two ways a shed comes down early.
- Local Law 11 explained: FISP requirements, covered buildings and the 2026 changesWhat the Facade Inspection Safety Program requires, which buildings it covers and who signs the report — including Local Law 49 of 2025, which replaces the five-year cycle with intervals of 6 to 12 years.
- Sidewalk shed permits in NYC: when one is required, and the 90-day ruleA shed is required for facade work more than 40 ft above curb level and whenever a dangerous condition exists. Since February 2026, permits last 90 days, renewals require an RDP progress report, and stalled sheds carry penalties that DOB expects to start imposing in early 2027.