After-Hours Variance (AHV) in NYC: nights, weekends and the three-business-day rule

Construction in New York runs from 7 am to 6 pm on weekdays. Work earlier, later or on a weekend needs an After-Hours Variance from DOB, filed at least three business days ahead. When it is needed, what to upload, what it costs and how renewals work.

Last checked: Oct 23, 2026

Key facts

  • Standard hours weekdays 7:00 am to 6:00 pm; any other time, including all weekend, needs an AHV
  • File by at least three business days before the first after-hours day — Wednesday for a Saturday or Sunday
  • Window any number of days within 14 consecutive days per application
  • Fees $130 to $650 filing fee by number of days, plus $80 for each after-hours day
  • Where DOB NOW: Build, from the work permit (Create AHV); eFiling for BIS jobs

When do you need an After-Hours Variance in NYC?

Whenever construction work happens before 7:00 am, after 6:00 pm, or on a Saturday or Sunday. For a DOB NOW job, the contractor requests the AHV in DOB NOW: Build from the work permit, at least three business days before the first after-hours day — by Wednesday for a Saturday or Sunday. One application can cover any days within 14 consecutive days. It costs a filing fee of $130 to $650, depending on the number of days, plus $80 for each after-hours day. The site’s Construction Noise Mitigation Plan must already be in place, and any DOT permit or DEP approval has to be uploaded with the application: DOB does not accept documents once it is submitted.

Key considerations

The hours

DOB requires an AHV for construction activity before 7:00 am, after 6:00 pm, or on a Saturday or Sunday. DEP’s noise rules say the same from the other side: construction is allowed between 7 am and 6 pm on weekdays, and at all other times, including any time on a weekend, it needs after-hours authorization. Work outside standard hours or on a weekend without an approved AHV is one of the conditions for which DOB may issue a full Stop Work Order.

Three business days ahead

The application must be filed at least three business days before the first intended work day. DOB’s own table: for work on a Saturday, Sunday or Monday, file by Wednesday; for Tuesday, by Thursday; for Wednesday, by Friday; for Thursday, by Monday; for Friday, by Tuesday. One application covers any number of days within a window of 14 consecutive days; days beyond it need a separate application.

Filing in DOB NOW: Build

The contractor starts the request from the dashboard with +Permits and then After Hours Variance, entering the permit number, or from the Work Permits dashboard with Create AHV on the permit’s row. Supporting documents — a DOT permit, a DEP-approved Certification of Undue Hardship, a DEP-approved Alternative Noise Mitigation Plan — are uploaded with +Add New Document before submitting, because documents are no longer accepted after the application is submitted. AHVs for jobs filed in BIS go through eFiling, and fee-exempt BIS jobs and DOB NOW elevator permits use a paper PW5 form at the borough office.

Several permits, one AHV

A combined AHV can cover several work permits when they all have the same applicant and are on the same BIN. At least one must be a DOB NOW permit, the request can list up to five job numbers, and Alt-3 BIS filings cannot be included. It is created from the dashboard with +New AHV Permit, not from a single filing’s row.

The fees

An initial AHV takes two payments. The filing fee pays for DOB’s review and depends on the number of days requested: $130 for 1 to 3 days, $260 for 4 to 6, $390 for 7 to 9, $520 for 10 to 12 and $650 for 13 or 14. After approval comes the work-permit fee of $80 for each day of after-hours work. Two weekends inside the 14-day window, Saturday and Sunday each, come to $260 plus 4 × $80, or $580.

After approval

DOB emails the contractor the outcome of the review. If approved, the contractor pays the daily fee in DOB NOW: Build and prints the permit from the Filing Action column; it can also be printed from the DOB NOW public portal without logging in, by searching the address and selecting the job. If denied, Trace History on the AHV application shows the reason. DOB’s After Hours Variance Map shows the projects allowed to work outside normal hours.

Renewals

A renewal is filed in DOB NOW: Build from the After Hours Variance dashboard with Renew AHV Permit, before the AHV permit expires. It can only cover the days approved in the initial request, or some of them: an AHV approved for Monday to Thursday can be renewed for Monday to Thursday, or just Tuesday, but not for Friday. DOB may limit renewal days at any time, and renewals are not available when the scope of work has changed, the licensee or contractor is not in good standing, or the job application has an issue that needs correcting. An expired AHV cannot be renewed; a new one is needed.

The noise plan comes first

DEP requires the site’s Construction Noise Mitigation Plan to be in place before an after-hours permit is sought from DOB or DOT. When strict compliance with the noise rules is not possible, an Alternative Noise Mitigation Plan is required, and the work it covers waits until DEP approves it. One route to after-hours work is undue hardship: under AC §24-223(e)(5), DOB or DOT may authorize it when DEP certifies that the permit holder has shown a hardship — unique site characteristics, unforeseen conditions, scheduling commitments or financial considerations outside its control — and has an approved Alternative Noise Mitigation Plan. DEP’s form warns that it will rescind that plan if DOB or DOT does not grant the after-hours approval. See noise and dust plans.

Checklist: before night or weekend work

  1. List the after-hours days and check that they fit in one 14-day window.
  2. Have the Construction Noise Mitigation Plan in place; if strict compliance is not possible, get DEP’s approval of an Alternative Noise Mitigation Plan first.
  3. Gather what must be uploaded with the application: the DOT permit for street work and any DEP approvals.
  4. File in DOB NOW: Build at least three business days before the first day — by Wednesday for a weekend.
  5. Once approved, pay the $80 daily fees and print the permit.
  6. Renew before the permit expires, for the same days or fewer; an expired AHV needs a new application.