FISP Cycle 10: who must file, and when
Buildings taller than six stories must file a Cycle 10 facade report, with the deadline set by the last digit of the tax block number. This guide covers the three filing windows, the fees, the penalties and the early-filing option for buildings with no Cycle 9 report.
Last checked: Oct 23, 2026
Key facts
- 10A tax blocks ending in 4, 5, 6 or 9 — February 21, 2025 to February 21, 2027
- 10B blocks ending in 0, 7 or 8 — February 21, 2026 to February 21, 2028
- 10C blocks ending in 1, 2 or 3 — February 21, 2027 to February 21, 2029
- Fees $425 initial or amended report; $305 extension; $140 penalty waiver request
- Late $1,000 a month; $5,000 a year when not filed
When is my FISP Cycle 10 report due?
Cycle 10 runs from February 21, 2025 to February 20, 2030 and applies to buildings taller than six stories. The filing window depends on the last digit of the tax block number: blocks ending in 4, 5, 6 or 9 file between February 21, 2025 and February 21, 2027 (Sub-Cycle 10A); blocks ending in 0, 7 or 8 between February 21, 2026 and February 21, 2028 (Sub-Cycle 10B); and blocks ending in 1, 2 or 3 between February 21, 2027 and February 21, 2029 (Sub-Cycle 10C). Reports are filed in DOB NOW: Safety by a DOB-approved Qualified Exterior Wall Inspector.
Key considerations
Identify the sub-cycle in one step
Take the last digit of the tax block number: 4, 5, 6 or 9 → Sub-Cycle 10A (February 21, 2025 to February 21, 2027); 0, 7 or 8 → 10B (February 21, 2026 to February 21, 2028); 1, 2 or 3 → 10C (February 21, 2027 to February 21, 2029). Not the address or the borough — the block.
Sub-Cycle 10A closes February 21, 2027
Buildings in 10A are in the final months of their window. SWARMP conditions from the previous cycle that have not been repaired must be reported as Unsafe in the Cycle 10 filing.
Taller than six stories
That is the threshold. The critical examination must be performed by a DOB-approved QEWI — not by the project manager and not by the contractor.
Buildings with no Cycle 9 report
Since December 15, 2025, owners whose most recent status is No Report Filed (NRF) and who will file as Safe or SWARMP may file their Cycle 10 initial report before their window opens, stopping further penalties; the sub-cycle override is no longer required. The option applies to Sub-Cycles 10B and 10C, and with 10B open since February 21, 2026, it now matters chiefly for 10C. Once the report is provisionally accepted, accrued penalties must be paid within 10 business days or the filing is deemed incomplete.
Filing fees
Initial report: $425. Amended or subsequent report: $425. Extension of time to complete repairs: $305. Request for a waiver of penalties: $140.
The cost of not filing
Late initial report: $1,000 per month. Failure to file: $5,000 per year. The penalty for missing the window exceeds the cost of the inspection. Unsafe and SWARMP conditions left uncorrected carry separate penalties, set out in Safe, SWARMP or Unsafe.
After Cycle 10
Local Law 49 of 2025, effective October 1, 2026, allows DOB to set future inspection intervals of 6 to 12 years by rule. The Cycle 10 deadlines are unchanged.
Checklist: Cycle 10
- Take the last digit of the tax block number and find the sub-cycle.
- Hire a DOB-approved QEWI early enough to file inside the window.
- Repair the Cycle 9 SWARMP items first: any still open must be reported Unsafe.
- No Cycle 9 report (NRF) and filing Safe or SWARMP? File early, and pay the penalties within 10 business days of provisional acceptance.
Sources
- 1 RCNY §103-04: periodic inspection of exterior walls (FISP)
- NYC DOB Service Notice, FISP Cycle 10 (February 24, 2025)
- NYC DOB Service Notice, FISP Cycle 10 follow-up: early filings for NRF buildings (December 8, 2025)
- NYC DOB, FISP Cycle 10 sub-cycle diagram
- NYC DOB, Façade compliance (Unsafe conditions, FISP1/FISP2/FISP3, public protection)
- NYC DOB, Façade fees and penalties
- 1 RCNY §101-03: DOB fees (shed progress report $90; facade extension and waiver fees)
- Local Law 49 of 2025: exterior wall inspection intervals (AC §28-302.2)
Checked against the official text on October 23, 2026.
Related guides
- Local Law 11 explained: FISP requirements, covered buildings and the 2026 changesWhat the Facade Inspection Safety Program requires, which buildings it covers and who signs the report — including Local Law 49 of 2025, which replaces the five-year cycle with intervals of 6 to 12 years.
- Safe, SWARMP or Unsafe: what each facade report classification requiresUnsafe starts a 90-day clock. SWARMP sets a firm completion date between one and five years out. What each classification commits the owner to — including the 2025 deadlines for sheds.
- The annual parapet observation: the NYC requirement most owners still missSince January 1, 2024, every building with a parapet fronting the public right-of-way — at any height — requires an annual observation, due by December 31. It is not filed with DOB and does not require an engineer.