How long do NYC sidewalk sheds stay up? An analysis of all 111,597 permits
The median sidewalk shed standing in New York City today has been up 796 days — 2.2 years — and three in ten have stood for more than five years. Figures computed from every DOB NOW shed permit, not from press reports.
Last checked: Oct 23, 2026
Key facts
- Data as of October 7, 2026 — NYC Open Data rbx6-tga4, DOB NOW: Build approved permits
- Sheds today 7,220 buildings with a valid shed permit
- Median standing time 796 days, or 2.2 years; 29% have stood more than five years
- Median permit 365 days; since February 2, 2026, permits last 90 days
- All permits 111,597 issued from October 18, 2017 to October 5, 2026
How long does a sidewalk shed stay up in New York City?
The median shed with a valid permit today has been standing for 796 days — about 2.2 years. Two-thirds have been up more than a year, half more than two years, and 29% more than five years. Across the data set, an individual shed permit ran a median of exactly 365 days, so a shed that has been up two years has been renewed; since February 2, 2026, new and renewed permits are limited to 90 days. As of October 7, 2026, 7,220 buildings in the city have a valid sidewalk shed permit.
Key considerations
7,220 buildings have a shed permit today
Manhattan 3,223 · Brooklyn 1,850 · Bronx 1,231 · Queens 854 · Staten Island 62. Since shed filings moved to DOB NOW: Build in October 2017, 41,245 different buildings have had one.
The median has been standing 2.2 years
796 days. 66% have been up more than one year, 52% more than two, 42% more than three, and 29% — 2,121 buildings — more than five years.
Permits ran one year; sheds did not
The median individual shed permit in the data ran exactly 365 days, and the median building with a shed today is on its third permit. One building in the city is on its 52nd shed permit. Under Local Law 48 of 2025, permits issued or renewed on or after February 2, 2026 last 90 days, so renewals per shed will rise sharply.
Penalties for long-standing sheds: expected from early 2027
Under Local Law 48 of 2025, from the second renewal a shed with no work in progress is penalized per linear foot per month, at a rate that rises with the shed’s age. DOB expects to begin imposing these penalties in early 2027. The rates are in our sidewalk shed permit guide.
Why this matters at bid
Shed rental is priced per linear foot per month, so the schedule is the cost. If the plan assumes six months and the city median is 2.2 years, the gap between those two numbers is someone’s margin — usually the contractor’s.
What these figures do not show
DOB NOW data begins in October 2017, so nine years is the limit of what the data can see, not the age of the oldest shed in New York; sheds filed in the legacy BIS system are not in this count. A valid permit is also not proof that a shed is physically standing — only that it is licensed to be.
Sources
- NYC Open Data, “DOB NOW: Build – Approved Permits” (rbx6-tga4)
- NYC DOB, DOB NOW: Build filing mandate for sheds, fences, supported scaffolds and signs (October 16, 2017)
- Local Law 48 of 2025: 90-day shed permits, progress reports and stalled-work penalties (AC §28-105.8.1, §28-220.1)
- NYC DOB Service Notice, “Local Law 48 and Local Law 51 of 2025: Sidewalk Shed Filing and Permit Changes in DOB NOW” (January 8, 2026)
- NYC Mayor’s Office, “Mamdani Administration Taking Down Sidewalk Sheds and Improving Design of New Sheds” (August 20, 2026)
Checked against the official text on October 23, 2026.
Related guides
- Sidewalk shed permits in NYC: when one is required, and the 90-day ruleA shed is required for facade work more than 40 ft above curb level and whenever a dangerous condition exists. Since February 2026, permits last 90 days, renewals require an RDP progress report, and stalled sheds carry penalties that DOB expects to start imposing in early 2027.
- NYC sidewalk shed renewal (2026 rules): the RDP report, the $220 fee and the weekly logSince August 13, 2026, a shed renewal needs an RDP’s in-person examination and progress report: $130 plus $90, or $220, and a $2,500 penalty when no acceptable report is filed. The contractor keeps the weekly work log.
- Safe, SWARMP or Unsafe: what each facade report classification requiresUnsafe starts a 90-day clock. SWARMP sets a firm completion date between one and five years out. What each classification commits the owner to — including the 2025 deadlines for sheds.