Construction hoist power: the electrical permit behind the hoist

A material or personnel hoist requires its own electrical permit for power, separate from the hoist equipment filing — a small line item that is routinely missed at bid.

Last checked: Oct 23, 2026

Key facts

  • Two permits the hoist itself (BC 3316.4) and its power (an electrical permit)
  • Power installed under a licensed electrician’s permit, filed in DOB NOW
  • Electrical code 2025 NYC Electrical Code, in full effect since December 21, 2025; Article 590 for temporary installations
  • Scaffold hoisting equipment over 2,000 lb on a supported scaffold needs the scaffold permit at any height

Does a construction hoist need an electrical permit?

Yes. When a project uses a hoist, powering it requires an electrical permit of its own, filed under a licensed electrician and separate from the equipment filing for the hoist itself.

Key considerations

Separate from the hoist filing

The hoist itself needs a DOB permit before it is installed (BC 3316.4; material and bucket hoists BC 3317, personnel hoists BC 3318). DOB treats a temporary hoist as construction equipment, not an elevator. Its power supply is a second permit and a second trade.

A licensed electrician

Temporary power for the hoist is installed under a licensed electrician’s permit, following the 2025 NYC Electrical Code (in full effect since December 21, 2025; Article 590 covers temporary installations).

Only when a hoist is specified

Most facade repair projects rely on suspended or supported scaffolds rather than a hoist; the permit applies only when a hoist is part of the access plan.

It also affects the scaffold permit

A supported scaffold with hoisting equipment rated over 2,000 lb loses the BC 3314.2 permit exemption, regardless of its height.

Price it with the hoist

Whenever a hoist appears in the access plan, include the electrical permit, the temporary power connection and the electrician’s time in the bid.

Checklist: a hoist on the job

  1. Check the access plan for a hoist: material, bucket or personnel.
  2. Price the hoist permit, the electrical permit, the temporary power connection and the electrician’s time.
  3. File the electrical permit for the hoist power under a licensed electrician.
  4. If the hoist sits on a supported scaffold and is rated over 2,000 lb, file the scaffold permit too.

Sources

Checked against the official text on October 23, 2026.