Key facts
- Two permits the hoist itself (BC 3316.4) and its power (an electrical permit)
- Power installed under a licensed electrician’s permit, filed in DOB NOW
- Electrical code 2025 NYC Electrical Code, in full effect since December 21, 2025; Article 590 for temporary installations
- Scaffold hoisting equipment over 2,000 lb on a supported scaffold needs the scaffold permit at any height
Does a construction hoist need an electrical permit?
Yes. When a project uses a hoist, powering it requires an electrical permit of its own, filed under a licensed electrician and separate from the equipment filing for the hoist itself.
Key considerations
Separate from the hoist filing
The hoist itself needs a DOB permit before it is installed (BC 3316.4; material and bucket hoists BC 3317, personnel hoists BC 3318). DOB treats a temporary hoist as construction equipment, not an elevator. Its power supply is a second permit and a second trade.
A licensed electrician
Temporary power for the hoist is installed under a licensed electrician’s permit, following the 2025 NYC Electrical Code (in full effect since December 21, 2025; Article 590 covers temporary installations).
Only when a hoist is specified
Most facade repair projects rely on suspended or supported scaffolds rather than a hoist; the permit applies only when a hoist is part of the access plan.
It also affects the scaffold permit
A supported scaffold with hoisting equipment rated over 2,000 lb loses the BC 3314.2 permit exemption, regardless of its height.
Price it with the hoist
Whenever a hoist appears in the access plan, include the electrical permit, the temporary power connection and the electrician’s time in the bid.
Checklist: a hoist on the job
- Check the access plan for a hoist: material, bucket or personnel.
- Price the hoist permit, the electrical permit, the temporary power connection and the electrician’s time.
- File the electrical permit for the hoist power under a licensed electrician.
- If the hoist sits on a supported scaffold and is rated over 2,000 lb, file the scaffold permit too.
Sources
- 2022 NYC Building Code, Chapter 33: Safeguards during construction or demolition
- NYC DOB, 2025 NYC Electrical Code (in full effect December 21, 2025)
- NYC DOB, Electrical permit
- NYC DOB, Temporary hoists
- NYC DOB, Project requirements for design professionals: temporary hoists
Checked against the official text on October 23, 2026.
Related guides
- Supported scaffold permits in NYC: the 40 ft thresholdA supported (pipe or frame) scaffold requires a permit at 40 ft or taller. Below 40 ft it generally does not — if it also meets all six conditions of the BC 3314.2 exemption.
- Sidewalk shed lighting: the electrical permit and the 2025 standardsEvery shed requires lighting installed by a licensed electrician under a separate permit. Since August 15, 2025: 1.5 foot-candles minimum, LED at 90 lumens per watt and shielding near windows.
- Suspended scaffold filings: from CD5 to DOB NOW, and the 24–48 hour noticeSince November 15, 2023, suspended scaffolds are filed in DOB NOW under the Suspended Scaffold (SC) work type, replacing the CD5. DOB must be notified 24 to 48 hours before installation and removal.