TPP or OPP: Tenant and Occupant Protection Plans in NYC
A Tenant Protection Plan covers occupied dwelling units and is filed with DOB; an Occupant Protection Plan covers occupied non-residential space and is kept on site. This guide also covers when the TPP is filed in DOB NOW and the BC 3310 site safety threshold for facade work.
Last checked: Oct 23, 2026
Key facts
- TPP any occupied dwelling unit (AC §28-120.1); prepared by an RDP
- When it is filed its own DOB NOW request, after the job filing is approved and before the work permit
- OPP occupied non-residential space (BC 3303.10); kept on site, not filed
- Facade site safety more than 14 stories or 200 ft, when the work needs a shed (BC 3310)
- Major building 7 or more stories or 75 ft, or a 100,000 sq ft footprint (since December 11, 2024)
What is the difference between a TPP and an OPP in NYC?
A Tenant Protection Plan (TPP) is required whenever a building has one or more occupied dwelling units — even when the work itself is in commercial space (AC §28-120.1, formerly §28-104.8.4). It is prepared by a Registered Design Professional and filed with DOB. An Occupant Protection Plan (OPP) records the protective measures for work in occupied non-residential space under BC 3303.10; it is not filed with or reviewed by DOB, but a copy must be available on site. In a mixed-use building, plan the protection of the non-residential occupants too, and confirm with the plan examiner whether it goes on the TPP or on a separate OPP.
Key considerations
TPP — residential
Occupied dwelling units trigger a Tenant Protection Plan. The party that prepares it (the RDP) and the party that implements it in the field (usually the general contractor) are different, and TPP compliance is also a special inspection under BC 1705.26. In DOB NOW the TPP is its own review request: it can be created and submitted only after the job filing is approved, and it must be approved before a work permit can be requested.
OPP — non-residential
Occupied commercial, institutional or assembly space requires an Occupant Protection Plan, kept on site for DOB inspectors.
Mixed use: confirm with the plan examiner
A building with apartments above and retail below needs protection for both groups of occupants. DOB’s 2020 TPP FAQ says an OPP is also required for the non-residential work, while BC 3303.10 lets the protective measures go on the TPP where one is required. Confirm with the plan examiner which document carries them.
Site safety for facade work: more than 14 stories
For facade alteration, maintenance or repair, BC 3310 site safety requirements apply when the building is more than 14 stories or 200 ft tall and the work requires a sidewalk shed. Full recladding requires a full-time Site Safety Manager.
“Major building” now starts at 7 stories
Since December 11, 2024 (Local Law 147 of 2021), a major building is one of 7 or more stories or 75 ft or more, or with a footprint of 100,000 sq ft or more, for new initial permits. What follows the new definition is the BC 3310 site safety requirements; on a major building under 15 stories and 200 ft, with a footprint of 100,000 sq ft or less, a Site Safety Coordinator may serve instead of a Site Safety Manager for construction, enlargement or demolition (BC 3310.5). A construction superintendent is still required by the type of job (BC 3301.13.3). DOB has confirmed the change does not alter the facade-work threshold above.
The bid set will not say
Bid documents rarely state that a building is occupied. Occupancy has to come from the building record, not from the drawings.
Checklist: an occupied building
- Check the building record for occupied apartments: if there are any, a TPP is required.
- Have the RDP prepare the TPP, and request it in DOB NOW once the job filing is approved.
- Get the TPP approved before requesting the work permit.
- For occupied commercial space, keep the protective measures (OPP or TPP) on site.
- Over 14 stories or 200 ft and with a shed: plan the BC 3310 site safety requirements.
Sources
- NYC Administrative Code, Title 28, Chapter 1: Administration (permits, §28-105; TPP, §28-120)
- 2022 NYC Building Code, Chapter 33: Safeguards during construction or demolition
- 2022 NYC Building Code, Chapter 17: Special inspections and tests
- NYC DOB, Tenant Protection Plan: frequently asked questions
- NYC DOB, TPP FAQs (2020)
- Local Law 147 of 2021: the major building definition
- NYC DOB Service Notice, “Local Law 147 of 2021: New Definition of Major Building” (2024)
- NYC DOB Buildings Bulletin 2026-006
Checked against the official text on October 23, 2026.
Related guides
- NYC special and progress inspections: the TR1 listThe 21 special inspections and 4 progress inspections most often listed on facade and alteration projects, with their code references and the project phase for each.
- SST cards (Local Law 196) for facade crews: who needs which card, and the Redcode deadlineWorkers need a 40-hour card and supervisors a 62-hour one on sites with a site safety professional, checked in the Training Connect app. Up to $5,000 per untrained worker. Redcode-issued training must be replaced by December 7, 2026.
- Filing a facade repair job in DOB NOW: Build: who files what, and in what orderThe RDP files an Alteration with the General Construction work type, DOB reviews it, the contractor pulls the work permit, and the job is signed off. Where sheds and scaffolds fit, and what must be ready first: LPC drawings, asbestos forms, the TPP.